- Home
- Departments
- Highway Department
- Current Highway Projects
Current Highway Projects
Project Map (PDF)
Project List
#1 – Paving of CSAH 15 and CSAH 30
Location: On CSAH 15 from the west county line (Minnesota River) for 2.75 miles east to approximately Minnesota River Drive SW & On CSAH 30 from the north county line for approximately 2.75 miles south
Description: Bituminous Paving
Contractor: Duininck Inc.
Approximate Start: May 30, 2023
Approximate Finish: August 2023
Project Update(s): Construction anticipated to begin after the Memorial Day Holiday with paving estimated to begin in July
#2 – Mill and Overlay of CSAH 15 and CSAH 41
Location: On CSAH 15 from approximately 1 mile west of MN 7/59 to 1st Street & on CSAH 41 from MN 7 to MN 29
Description: Mill and Overlay
Contractor: Duininck Inc.
Approximate Start: May 30, 2023
Approximate Finish: August 2023
Project Update(s): Construction anticipated to begin in June with paving estimated to begin in July
#3 – Replace Bridges
Location: On 50th Ave SE between CSAH 5 and CSAH 4 1 mile west of Gluek & on 90th Street SE between TH 23 and CSAH 4, 1 mile south of Maynard
Description: Replacement of timber bridge and concrete pipe with new concrete box culverts
Contractor: John Riley Construction, Inc.
Approximate Start: Fall 2023
Approximate Finish: Summer 2024
Project Update(s): Project under contract. Waiting for box culverts to be build by manufacture.
#4 – Replace Bridge
Location: 1.3 miles east of CSAH 3 on 70th Street SE over Hawk Creek Floodway 3 miles Southwest of Clara City, MN
Description: Replace timber bridge with new concrete bridge
Contractor: Structural Specialties, Inc.
Approximate Start: May 15, 2023
Approximate Finish: August 2023
Project Update(s): Construction began on May 15th.
#5 – Seal Coating
Location: Wegdahl Bike Trail, CSAH 5/38 (Granite Falls)
Description: Application of seal coat material
Contractor: Gee Asphalt Systems, Inc. from Cedar Rapids, IA
Approximate Start: June 2023
Approximate Finish: July 2023
Project Update(s): Carry over project from 2022. Contractor will be back in 2023 to finish work on CSAH 5/38 and on the Wegdahl Bike Trail
#6 – Aggregate Surfacing
Location: County Roads 11, 12, 33, 34, 35
Description: Crushing, Hauling and Placing Class 5 Gravel Aggregate
Contractor: R & G Construction Co.
Approximate Start: TBD
Approximate Finish: October 2023
Project Update(s): Project under contract.
#7 – Re-Construction of CSAH 4 (old MN 277)
Location: On CSAH 4 from CSAH 13 to MN 40
Description: Grading, drainage, and aggregate base
Contractor: TBD
Approximate Start: 2024
Approximate Finish: 2024
Project Update(s): Project in final design and utility coordination phase.
#8 – Pavement Marking
Location: County Wide
Description: Marking of centerline and edge lines on county roads
Contractor: Traffic Solutions Incorporated
Approximate Start: May 2023
Approximate Finish: September 2023
Project Update(s): Contractor will begin marking roads in May 2023 and will then return later in the summer to mark the remaining roads after seal coating operations.
#9 – Seal Coating
Location: County Roads 1, 2, & 13
Description: Seal Coating
Contractor: County Forces
Approximate Start: June/July 2023
Approximate Finish: August 2023
Project Update(s):