Current Highway Projects

road-construction-type-barricades-traffic-safety-store
2022 Construction Map_numbers_website

Project Map (PDF)

Project List


#1 – Re-Construction of CSAH 15

  

                  Location:  On CSAH 15 from the west county line (Minnesota River) for 2.75 miles east to approximately Minnesota River Drive SW

              Description:   Grading, drainage and aggregate base

               Contractor:   Kern & Tabery from Wadena, MN

   Approximate Start:   June 2022

 Approximate Finish:   November 2022

                     Detour:    See Map (PDF) 

    Project Update(s):   Contractor scheduled to begin work in July

                                    Public Meeting May 23, 2022 (PDF)

                                      7/14/2022 Update: Constructed scheduled to begin July 25, 2022

                                      7/20/2022: Press Release (PDF) Road Construction Begins July 25, 2022.

                                       8/3/2022: NOTICE: Temporary Mailbox Relocation

#2 – Re-Construction of CSAH 30

                                

                  Location:   On CSAH 30 from the north county line for approximately 2.75 miles south 

              Description:   Grading, drainage and aggregate base

               Contractor:   Kern & Tabery from Wadena, MN

   Approximate Start:   June 2022

 Approximate Finish:   November 2022

    Project Update(s):   Contractor scheduled to begin work in June

                                    Public Meeting May 23, 2022 (PDF) 


                                    7/14/2022 Update: Construction began June 1, 2022. Contractor scheduled to complete earthwork operations by end of July, weather depending.


                                   8/15/2022 UPDATE: The Contractor has completed the work. Paving will be in 2023.

                                      

#3 – Mill and Overlay of CSAH 16

 

                  Location:   On CSAH 16 from CSAH 5 to CSAH 15 (approximately 8 miles) 

              Description:   Milling and new bituminous pavement

               Contractor:   Central Specialties, Inc. from Alexandria, MN

   Approximate Start:   September 2022

 Approximate Finish:   October 2022

    Project Update(s):  Update 9/12/2022: The Contractor will begin milling on CSAH 4 on 9/12/2022. Milling operations anticipated the  week of 9/12 and 9/19.

  

#4 – Mill and Overlay of CSAH 4

 

                  Location:   On CSAH 4 from TH 7 to N City Limits of Maynard & from TH 23 to south county line

              Description:   Leveling course, underseal, milling and new bituminous pavement

               Contractor:   Central Specialties, Inc. from Alexandria, MN

   Approximate Start:   September 2022

 Approximate Finish:   October 2022

    Project Update(s):   UPDATE 9/9/2022: The Contractor is scheduled to begin milling on CSAH 4 on 9/12/2022 starting at the south county line and working north. Expect delays when traveling through construction zones. 


#5 – Seal Coating

                   Location:   Wegdahl Bike Trail, CSAH 21 (Milan), CSAH 9 (Watson), CSAH 42 (Montevideo), CSAH 5 (Granite Falls),                                               CSAH 38 (Granite Falls)

              Description:   Application of seal coat material

               Contractor:   Gee Asphalt Systems, Inc. from Cedar Rapids, IA

   Approximate Start:   Late August

 Approximate Finish:   Mid-September 2022

    Project Update(s):   UPDATE 9/6/2022: Start date is scheduled for September 13, 2022, weather depending. Work is scheduled to begin in Milan. 


 
#6 – Aggregate Surfacing

 

                  Location:   CSAH 5, CSAH 7, and CSAH 12

              Description:   Crushing, Hauling and Placing Class 5 Gravel Aggregate

               Contractor:   Wm. D. Scepaniak Inc. from Holdingford, MN 

   Approximate Start:   August 2022

 Approximate Finish:   September 2022

    Project Update(s):  UPDATE 8/19/2022: Contractor scheduled to begin the week of August 29, 2022.

                                   UPDATE 9/6/2022: Contractor began crushing 8/29/2022. Hauling and placing anticipated the week of  September 5, 2022.

                                   UPDATE 9/12/2022: The Contractor is scheduled to begin hauling and placing gravel starting on 9/13/2022. 


 

#7 – Replace Bridges

 

                  Location:   On CSAH 12 approximately 1/4 mile east of the intersection of CSAH 12 & CSAH 6 and on CSAH 12                   approximately 1/4 mile west of the intersection of CSAH 12 and 20th Ave NW

              Description:   Replacement of timber bridges with new concrete box culverts

               Contractor:   Riley Brothers Construction from Morris, MN

   Approximate Start:   Estimated Start date is 8/29/2022

 Approximate Finish:   Mid September 2022

    Project Update(s):   8/12/2022 UPDATE: Contractor is scheduled to begin construction around August 29, 2022.

                                    8/19/2022 UPDATE: The Contractor moved up the start date and started construction on August 19, 2022. 

Public Notice (PDF)

                                     9/6/2022 UPDATE: The Contractor completed the bridge on CSAH 12 located approximately 1//4 mile west of the                                                 intersection of CSAH 12 & 20th Ave NW. Work began on the second bridge on 9/1/2022. 

#8 – Pavement Marking

                  Location:   County Wide

              Description:   marking of centerline and edge lines on county roads

               Contractor:   Sir Lines-A-Lot from Edina, MN

   Approximate Start:   September 2022

 Approximate Finish:   October 2022

    Project Update(s):   

 

#9 – CSAH 16 Railroad Crossing (Not shown on the map)

 

                  Location:   Between US 212 and CSAH 16

              Description:   installation of a new concrete panel crossing and paving about 300 feet of CSAH 16

               Contractor:   Joe Riley Construction from Morris, MN

   Approximate Start:   August 10, 2022

 Approximate Finish:   August 19, 2022

    Project Update(s):  8/17/2022: The project was completed on 8/15/2022.