Current Highway Projects

road-construction-type-barricades-traffic-safety-store
2022 Construction Map_numbers_website

Project Map (PDF)

Project List


#1 – Re-Construction of CSAH 15

  

                  Location:  On CSAH 15 from the west county line (Minnesota River) for 2.75 miles east to approximately Minnesota River Drive SW

              Description:   Grading, drainage and aggregate base

               Contractor:   Kern & Tabery from Wadena, MN

   Approximate Start:   June 2022

 Approximate Finish:   November 2022

                     Detour:    See Map (PDF) 

    Project Update(s):   Contractor scheduled to begin work in July

                                    Public Meeting May 23, 2022 (PDF)

                                      7/14/2022 Update: Constructed scheduled to begin July 25, 2022

                                      7/20/2022: Press Release (PDF) Road Construction Begins July 25, 2022.

                                       8/3/2022: NOTICE: Temporary Mailbox Relocation

                                      10/24/2022: Project Update

#2 – Re-Construction of CSAH 30

                  Location:   On CSAH 30 from the north county line for approximately 2.75 miles south 

              Description:   Grading, drainage and aggregate base

               Contractor:   Kern & Tabery from Wadena, MN

   Approximate Start:   June 2022

 Approximate Finish:   November 2022

    Project Update(s):   Contractor scheduled to begin work in June

                                    Public Meeting May 23, 2022 (PDF) 


                                    7/14/2022 Update: Construction began June 1, 2022. Contractor scheduled to complete earthwork operations by end of July, weather depending.


                                   8/15/2022 UPDATE: The Contractor has completed the work. Paving will be in 2023.

                                      

#3 – Mill and Overlay of CSAH 16

 

                  Location:   On CSAH 16 from CSAH 5 to CSAH 15 (approximately 8 miles) 

              Description:   Milling and new bituminous pavement

               Contractor:   Central Specialties, Inc. from Alexandria, MN

   Approximate Start:   September 2022

 Approximate Finish:   October 2022

    Project Update(s):  Update 9/12/2022: The Contractor will begin milling on CSAH 4 on 9/12/2022. Milling operations anticipated the  week of 9/12 and 9/19.


                                   Update 10/24/2022: The Contractor has completed the project on October 14, 2022.


#4 – Mill and Overlay of CSAH 4

 

                  Location:   On CSAH 4 from TH 7 to N City Limits of Maynard & from TH 23 to south county line

              Description:   Leveling course, underseal, milling and new bituminous pavement

               Contractor:   Central Specialties, Inc. from Alexandria, MN

   Approximate Start:   September 2022

 Approximate Finish:   October 2022

    Project Update(s):   UPDATE 9/9/2022: The Contractor is scheduled to begin milling on CSAH 4 on 9/12/2022 starting at the south county line and working north. Expect delays when traveling through construction zones. 


                                   Update 10/24/2022: The Contractor has completed the project on October 14, 2022. 


#5 – Seal Coating

                   Location:   Wegdahl Bike Trail, CSAH 21 (Milan), CSAH 9 (Watson), CSAH 42 (Montevideo), CSAH 5 (Granite Falls),                                               CSAH 38 (Granite Falls)

              Description:   Application of seal coat material

               Contractor:   Gee Asphalt Systems, Inc. from Cedar Rapids, IA

   Approximate Start:   Late August

 Approximate Finish:   Mid-September 2022

    Project Update(s):   UPDATE 9/6/2022: Start date is scheduled for September 13, 2022, weather depending. Work is scheduled to begin in Milan. 

                                 Update 10/24/2022: The Contractor has completed the work in Milan, Watson, Montevideo streets. The                                                  Contractor will be back in early summer of 2023 to complete seal coating in Granite Falls and on the Wegdahl                                       Bike Trail. 


 
#6 – Aggregate Surfacing

                  Location:   CSAH 5, CSAH 7, and CSAH 12

              Description:   Crushing, Hauling and Placing Class 5 Gravel Aggregate

               Contractor:   Wm. D. Scepaniak Inc. from Holdingford, MN 

   Approximate Start:   August 2022

 Approximate Finish:   September 2022

    Project Update(s):  UPDATE 8/19/2022: Contractor scheduled to begin the week of August 29, 2022.

                                   UPDATE 9/6/2022: Contractor began crushing 8/29/2022. Hauling and placing anticipated the week of  September 5, 2022.

                                   UPDATE 9/12/2022: The Contractor is scheduled to begin hauling and placing gravel starting on 9/13/2022. 

                                   UPDATE 10/24/2022: The Contractor has completed this project.  

 

#7 – Replace Bridges

 

                  Location:   On CSAH 12 approximately 1/4 mile east of the intersection of CSAH 12 & CSAH 6 and on CSAH 12                   approximately 1/4 mile west of the intersection of CSAH 12 and 20th Ave NW

              Description:   Replacement of timber bridges with new concrete box culverts

               Contractor:   Riley Brothers Construction from Morris, MN

   Approximate Start:   Estimated Start date is 8/29/2022

 Approximate Finish:   Mid September 2022

    Project Update(s):   8/12/2022 UPDATE: Contractor is scheduled to begin construction around August 29, 2022.

                                    8/19/2022 UPDATE: The Contractor moved up the start date and started construction on August 19, 2022. 

Public Notice (PDF)

                                     9/6/2022 UPDATE: The Contractor completed the bridge on CSAH 12 located approximately 1//4 mile west of the                                                 intersection of CSAH 12 & 20th Ave NW. Work began on the second bridge on 9/1/2022. 

                                     10/24/2022 UPDATE: Both Bridges have been completed. 

#8 – Pavement Marking

                  Location:   County Wide

              Description:   marking of centerline and edge lines on county roads

               Contractor:   Sir Lines-A-Lot from Edina, MN

   Approximate Start:   September 2022

 Approximate Finish:   October 2022

    Project Update(s):   10/24/2022: The Contractor has completed the pavement markings on October 17, 2022.

 

#9 – CSAH 16 Railroad Crossing (Not shown on the map)

 

                  Location:   Between US 212 and CSAH 16

              Description:   installation of a new concrete panel crossing and paving about 300 feet of CSAH 16

               Contractor:   Joe Riley Construction from Morris, MN

   Approximate Start:   August 10, 2022

 Approximate Finish:   August 19, 2022

    Project Update(s):  8/17/2022: The project was completed on 8/15/2022.