Current Highway Projects

road-construction-type-barricades-traffic-safety-store
2023 Construction Map_2023 map

Project Map (PDF)

Project List


#1 – Paving of CSAH 15 and CSAH 30

 

                  Location:   On CSAH 15 from the west county line (Minnesota River) for 2.75 miles east to approximately Minnesota River Drive SW & On CSAH 30 from the north county line for approximately 2.75 miles south

              Description:   Bituminous Paving 

               Contractor:   Duininck Inc.

   Approximate Start:   May 30, 2023

 Approximate Finish:   August 2023

    Project Update(s):  Construction anticipated to begin after the Memorial Day Holiday with paving estimated to begin in July

  6/25/2023 Update: Grading and placement of gravel to begin on Monday, 6/26/2023 on County Road 15. Expect delays. Click here for more information.                                                       

  6/25/2023 Update: Road Closure of a portion of County Road 15 begins on Tuesday, 6/27/2023. Click here for more information.

   6/29/2023 Update: County Road 15 was opened to traffic around 8pm on Wednesday, June 28, 2023.

   6/29/2023 Update: Grading and placement of gravel on County Road 30 to begin on Thursday, June 29, 2023. Click here for more information. 

     9/5/2023 Update: Topsoil placement, in-slope grading, seeding, and erosion control scheduled to begin on Thursday, September 7, 2023. Final completion estimated by September 15, 2023. 

 

 

#2 – Mill and Overlay of CSAH 15 and CSAH 41

 

                  Location:   On CSAH 15 from approximately 1 mile west of MN 7/59 to 1st Street & on CSAH 41 from MN 7 to MN 29 

              Description:   Mill and Overlay

               Contractor:   Duininck Inc.

   Approximate Start:   May 30, 2023

 Approximate Finish:   August 2023

    Project Update(s):   Construction anticipated to begin early July with paving estimated to begin after the July 4th Holiday.

    9/5/2023 Update: Work completed in August 2023.

 

 

#3 – Replace Bridges

 

                  Location:   On 50th Ave SE between CSAH 5 and CSAH 4 1 mile west of Gluek & on 90th Street SE between TH 23 and CSAH 4, 1 mile south of Maynard

              Description:   Replacement of timber bridge and concrete pipe with new concrete box culverts

               Contractor:   John Riley Construction, Inc.

   Approximate Start:   Fall 2023

 Approximate Finish:   Summer 2024

    Project Update(s):  Project under contract. Waiting for box culverts to be build by manufacture. 

    9/5/2023 Update:  90th Street SE box culvert project started on August 25, 2023 and completed on August 30, 2023. The 50th Ave SE box culvert project started on August 30, 2023. Estimated completion date of September 8, 2023. 


 
#4 – Replace Bridge

                   Location:   1.3 miles east of CSAH 3 on 70th Street SE over Hawk Creek Floodway 3 miles Southwest of Clara City, MN

              Description:   Replace timber bridge with new concrete bridge

               Contractor:   Structural Specialties, Inc. 

   Approximate Start:   May 15, 2023

 Approximate Finish:   August 2023

    Project Update(s):  Construction began on May 15th

  6/25/2023 Update:  The bridge deck was poured on June 20, 2023. Estimated bridge opening is in 30 to 45 days.

    9/5/2023 Update: Topsoil placement, in-slope grading, seeding, and erosion control scheduled to begin on Thursday, September 7, 2023. Final completion estimated by September 15, 2023. 

 

 

#5 – Seal Coating

 

                  Location:   Wegdahl Bike Trail, CSAH 5/38 (Granite Falls)

              Description:   Application of seal coat material

               Contractor:   Gee Asphalt Systems, Inc. from Cedar Rapids, IA

   Approximate Start:   June 2023

 Approximate Finish:   July 2023

    Project Update(s):   Carry over project from 2022. Contractor will be back in 2023 to finish work on CSAH 5/38 and on the Wegdahl Bike Trail

    9/5/2023 Update:  Project Started on August 21, 2023 and completed on August 24, 2023.

 

 

#6 – Aggregate Surfacing

 

                  Location:   County Roads 11, 12, 33, 34, 35

              Description:   Crushing, Hauling and Placing Class 5 Gravel Aggregate

               Contractor:   R & G Construction Co. 

   Approximate Start:   TBD

 Approximate Finish:   October 2023

    Project Update(s):   Project under contract. 

 

 

#7 – Re-Construction of CSAH 4 (old MN 277)

 

                  Location:   On CSAH 4 from CSAH 13 to MN 40

              Description:   Grading, drainage, and aggregate base

               Contractor:   TBD

   Approximate Start:   2024

 Approximate Finish:   2024

    Project Update(s):   Project in final design and utility coordination phase.

 

 

#8 – Pavement Marking

 

                  Location:   County Wide

              Description:   Marking of centerline and edge lines on county roads

               Contractor:   Traffic Solutions Incorporated

   Approximate Start:   May 2023

 Approximate Finish:   September 2023

    Project Update(s):   Contractor will begin marking roads in May 2023 and will then return later in the summer to mark the remaining roads after seal coating operations. 

    9/5/2023 Update: Project completed in August 2023.

 

#9 – Seal Coating

 

                  Location:   County Roads 1, 2, & 13

              Description:   Seal Coating 

               Contractor:   County Forces

   Approximate Start:   June/July 2023

 Approximate Finish:   August 2023

    Project Update(s):   Project was started on June 12, 2023. Remaining work is to fog seal on top of the chip seal. Fog seal planned for late July.

     9/5/2023 Update: Project completed in August 2023.